Project Duration
Stipulated Date of Commencement
March 08 2019
Stipulated Date of Completion /
Likely Date of Completion August 07 2019
Likely Date of Completion August 07 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 21,604,390.00
Awarded for
₹ 21,378,699.00
Project highlights
Up- gradation of the existing Laboratory facilities
Contractors
M/s. Bioxia
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Renovation/alteration of DIET Building for Goa Human Resource Development Corporation at Porvorim, Goa
View Project
Construction of Multi Purpose Community Hall for Department of Tribal Welfare at Harvalem Sankhali, Bicholim Taluka
View Project
Air conditioning works.