Project Duration
Stipulated Date of Commencement
October 31 2013
Stipulated Date of Completion /
Likely Date of Completion November 14 2013
Likely Date of Completion November 14 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,068,832.00
Awarded for
₹ 16,497,320.00
Project highlights
Erection of temporary Hanger for hosting the Inaugural and Closing ceremonies of Internation Film Faestival of India (IFFI) 2013.
Contractors
M/s. RMB Event Management Pvt. Ltd.
Consultants
In-house (GSIDC)