Project Duration
Stipulated Date of Commencement
December 02 2010
Stipulated Date of Completion /
Likely Date of Completion December 17 2010
Likely Date of Completion December 17 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,940,292.00
Awarded for
₹ 2,940,292.00
Contractors
M/s. Richo Limited
Consultants
In-house (GSIDC)