Project Duration
Stipulated Date of Commencement
February 19 2010
Stipulated Date of Completion /
Likely Date of Completion October 18 2010
Likely Date of Completion October 18 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 49,680,288.00
Awarded for
₹ 46,380,920.00
Contractors
M/s. Indecor Slides (I) Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.