Project Duration
Stipulated Date of Commencement
October 29 2008
Stipulated Date of Completion /
Likely Date of Completion March 28 2010
Likely Date of Completion March 28 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 133,955,490.42
Awarded for
₹ 211,937,309.40
Project highlights
An RCC framed G+3 auditorium building which consists of a centrally air conditioned auditorium with a capacity of 768 seats (591 seats in ground floor and 177 seats in balcony)., Green rooms, Rehersal rooms, a mini theatre with a capacity of 170 seats, toilets for ladies , gents and handicapped on each floor, Set storage room ect. and the related facilities like a G+2 Canteen building having administrative area at ground floor, canteen on the first floor and Ladies and gents dormitory and three guest rooms on the second floor.
Contractors
M/s.Silpa Projects and Infrastructure (I) Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.,
See Similar Projects
Construction of Community Hall in the Morlem Rehabilitation Colony in Sattari Taluka
View Project
HVAC Works.
View Project
Development of Open space near Palmar Apartment
View Project