Project Duration
Stipulated Date of Commencement
October 29 2008
Stipulated Date of Completion /
Likely Date of Completion March 28 2010
Likely Date of Completion March 28 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 133,955,490.42
Awarded for
₹ 211,937,309.40
Project highlights
An RCC framed G+3 auditorium building which consists of a centrally air conditioned auditorium with a capacity of 768 seats (591 seats in ground floor and 177 seats in balcony)., Green rooms, Rehersal rooms, a mini theatre with a capacity of 170 seats, toilets for ladies , gents and handicapped on each floor, Set storage room ect. and the related facilities like a G+2 Canteen building having administrative area at ground floor, canteen on the first floor and Ladies and gents dormitory and three guest rooms on the second floor.
Contractors
M/s.Silpa Projects and Infrastructure (I) Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.,
See Similar Projects
Setting up of software technology park at Udyog Bhavan, Panaji, Goa- Dismantling civil and plumbing works
View Project
Landscaping work
View Project
Rejuvenation of cluster of lanes of Altinho Steps Phase II
View Project