Project Duration
Stipulated Date of Commencement May 28 2016
Stipulated Date of Completion /
Likely Date of Completion
August 27 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 11,218,865.00
Awarded for ₹ 14,517,738.16

Project highlights

Re-construction of Market Complex-Cum-Community Hall .
(1) There are 10 nos. of shops of size 5mts x 3mtr with separate toilet facilities on the Ground floor.
(2) Mini Hall of size 19.920 x 9.44 mtr with capacity of 200 persons.
(3) Two Changing Room and Stage of 4.48 mtr x 5.86 mtr.