Project Duration
Stipulated Date of Commencement
October 25 2013
Stipulated Date of Completion /
Likely Date of Completion November 14 2013
Likely Date of Completion November 14 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 384,228.00
Awarded for
₹ 390,000.00
Project highlights
The scope of work involved servicing of 750kVA DG set and 750kVA Transformer.
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
UCJ architecture & environment
See Similar Projects
Panaji to Pollem (Part I) – Chainage 0.00 km. to 31.30 km.
View Project
Construction of new building for SCERT at Porvorim, Goa
View Project
Additional electrical and networking work.
View Project





