Project Duration
Stipulated Date of Commencement October 25 2013
Stipulated Date of Completion /
Likely Date of Completion
November 14 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 384,228.00
Awarded for ₹ 390,000.00

Project highlights

The scope of work involved servicing of 750kVA DG set and 750kVA Transformer.

 
Gallery Image
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Gallery Image
Consultants
UCJ architecture & environment
 
Similar Projects

See Similar Projects

Similar Project

Supply, installation, testing and commissioning of 315 KVA transformer.

View Project
Similar Project

Repairs and painting of D. B. Marg and other roads for IFFI 2014.

View Project
Similar Project

Urgent repairs of the existing lift in the building Essar Trade Centre, Morod, Mapusa, Bardez-Goa, wherein the office of Sub-registrar is situated

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.