Project Duration
Stipulated Date of Commencement February 12 2015
Actual Date of Completion October 14 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 35,524,278.45
Awarded for ₹ 32,955,460.00
Final Cost of Project ₹ 26,557,361.00

Project highlights

Upgraded premises for the Goa Human Resource Development Corporation at Porvorim, Goa

 
Contractors
M/s. Concept Creator,
Consultants
M/s. Shiva Consultancy Services Pvt. Ltd.,
 

See Similar Projects

Full Renovation And Part Construction Of The Old Heritage Building Of Asilo Hospital For State Health Training Institute At Mapusa. SH-External Lighting Work

View Project

Providing 11 kV transformer substation for release of electrical connection to the office premises of Commercial Tax Office, Ponda .

View Project

False Ceiling, Acoustical Paneling and Miscellaneous Works

View Project
x