Project Duration
Stipulated Date of Commencement
July 07 2013
Stipulated Date of Completion /
Likely Date of Completion August 06 2013
Likely Date of Completion August 06 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,12,103.00
Awarded for
₹ 21,94,753.54
Project highlights
Premonsoon works
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.,
See Similar Projects
Supply, Testing and Commissioning of Anaesthesia Workstation
View Project
Upgradation of NICU at Goa Medical College, Bambolim-Goa – Office Furniture
View Project
Furniture works.