Project Duration
Stipulated Date of Commencement
June 16 2012
Stipulated Date of Completion /
Likely Date of Completion September 13 2012
Likely Date of Completion September 13 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,183,092.00
Awarded for
₹ 14,742,636.40
Project highlights
Furniture work
Contractors
M/s. Floor-Space
Consultants
Datta Kare Associates