Project Duration
Stipulated Date of Commencement December 16 2015
Stipulated Date of Completion /
Likely Date of Completion
February 15 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,335,171.00
Awarded for ₹ 5,277,777.00

Project highlights

Acoustic works in Auditorium

 
Gallery Image
Contractors
M/s. Harshada Trading Company
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 
Similar Projects

See Similar Projects

Similar Project

– Supply, Installation, Testing & Commissioning of Solar Water Heating System”.

View Project
Similar Project

Upgradation of Primary Health Centre at Shiroda, Goa – Civil, Plumbing, Electrical, Elevators, Fire Fighting and Landscaping works

View Project
Similar Project

Civil, Plumbing & Internal Electrical works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.