Project Duration
Stipulated Date of Commencement July 15 2004
Stipulated Date of Completion /
Likely Date of Completion
July 14 2005
Status
100%
Completed
Cost (₹)
Estimated at ₹ 44,176,740.00
Awarded for ₹ 43,420,441.00

Project highlights

The library building wraps itself around the existing trees and takes maximum advantage of natural North light. Terraces at various levels expand the internal volumes visually into the landscape, thereby making reading in the library so much more comfortable and pleasurable. Each level is provided with a mezzanine level to maximize stacking area. These mezzanine levels are so designed, that books are easily within reach. Separate spaces are allocated for PhD. & faculty, night reading etc. A dedicated seminar room is also provided. The existing ground slope is effectively used to create a semi basement, which is used for stacking and storage of archives.

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 
Similar Projects

See Similar Projects

Similar Project

Minor Maintenance / Renovation works at Hospitals, Health Centres and Institutions under Directorate of Health Services, in the State of Goa – Roofing Works for District Hospital, Mapusa-Goa

View Project
Similar Project

External electrical work at area around new Library Building and Power supply to new Library Building, GMC Complex, Bambolim, Goa – Supply, laying of 1100 V power supply cable.

View Project
Similar Project

Supply, Installation, Testing and Commissioning of Stress test machine

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.