Project Duration
Stipulated Date of Commencement
March 30 2017
Stipulated Date of Completion /
Likely Date of Completion April 29 2017
Likely Date of Completion April 29 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,994,303.00
Awarded for
₹ 2,811,520.00
Project highlights
Providing furniture such as beds, compactors, racks, TV, Printer, Desks, etc.
Contractors
M/s. Amardeep Designers India Pvt. Ltd.
Consultants
M/s. Datta Kare Associates