Project Duration
Stipulated Date of Commencement
February 14 2020
Stipulated Date of Completion /
Likely Date of Completion September 07 2020
Likely Date of Completion September 07 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,859,392.72
Awarded for
₹ 1,997,827.88
Project highlights
Supply and installation of lead doors
Contractors
M/s. Manup Infrastructures
Consultants
M/s. KICONS Limited