Project highlights
RCC five storeyed building.
Ground Floor : Casualty ward & morgue, O.T.
First Floor : Consulting rooms.
Second Floor : Surgical wards, OT (04 nos.), ICU.
Third Floor : Pediatric wards, gynecology wards, antenatal ward, post natal wards, OT, special & twin private rooms.
Fourth Floor : Medicine Ward (Male & Female), ICCU, Conference Room.
Contractors
Consultants
Sub Works
This project involved 14 sub works. The details of the same available below
Civil, Plumbing & Internal Electrical works.
Likely Date of Completion December 19 2012
Project highlights
RCC five storeyed building.
Ground Floor : Casualty ward & morgue, O.T.
First Floor : Consulting rooms.
Second Floor : Surgical wards, OT (04 nos.), ICU.
Third Floor : Pediatric wards, gynecology wards, antenatal ward, post natal wards, OT, special & twin private rooms.
Fourth Floor : Medicine Ward (Male & Female), ICCU, Conference Room.
Contractors
Consultants
Lifts.
Likely Date of Completion September 13 2012
Contractors
Consultants
Fire Fighting, Fire Alarm & Public Address System
Likely Date of Completion November 30 2012
Contractors
Consultants
Air Conditioning.
Likely Date of Completion September 30 2012
Contractors
Consultants
Substation & external electrical works.
Likely Date of Completion September 30 2012
Contractors
Consultants
DG work.
Likely Date of Completion August 17 2012
Contractors
Consultants
Interior works – Phase I.
Likely Date of Completion December 19 2012
Contractors
Consultants
Steel Operation Theatre.
Likely Date of Completion September 07 2012
Contractors
Consultants
Medical gas & vacuum plant.
Likely Date of Completion October 05 2012
Contractors
Consultants
Surveillance & Audio Video System.
Likely Date of Completion September 04 2012
Contractors
Consultants
Networking, EPABX, UPS, Nurse Calling System, OPD System & Additional Electrical work.
Likely Date of Completion October 05 2012
Contractors
Consultants
Supply, Installation, Testing & Commissioning of Mortuary Cabinets.
Likely Date of Completion December 20 2011
Contractors
Consultants
Interior works – Phase II.
Likely Date of Completion December 19 2012
Contractors
Consultants
Landscaping work
Likely Date of Completion December 19 2012
Contractors
Consultants