Project Duration
Stipulated Date of Commencement October 29 2019
Stipulated Date of Completion /
Likely Date of Completion
January 08 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 917,160.00
Awarded for ₹ 882,270.00
 
Gallery Image
Contractors
M/S. Power Engineering (India) Pvt Ltd
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Air conditioning works

View Project
Similar Project

Interior Works

View Project
Similar Project

Procurement of Equipment for the Burns Unit (New Ward 118), Department of Plastic Surgery, Goa Medical College, Bambolim – Goa- SH-Supply, Installation, Testing and Commissioning of Operation Table

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.