Project Duration
Stipulated Date of Commencement
October 29 2019
Stipulated Date of Completion /
Likely Date of Completion January 08 2020
Likely Date of Completion January 08 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 917,160.00
Awarded for
₹ 882,270.00
Contractors
M/S. Power Engineering (India) Pvt Ltd
Consultants
In-house (GSIDC)