Project Duration
Stipulated Date of Commencement
August 18 2009
Stipulated Date of Completion /
Likely Date of Completion February 17 2010
Likely Date of Completion February 17 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 61,06,052.00
Awarded for
₹ 7,020,395.00
Contractors
M/s. Japsin Jacob Wire Drawing Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.