Project Duration
Stipulated Date of Commencement
January 24 2019
Stipulated Date of Completion /
Likely Date of Completion May 23 2019
Likely Date of Completion May 23 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,414,718.00
Awarded for
₹ 14,597,625.70
Project highlights
False Ceiling, Acoustical Paneling and Miscellaneous Works
Contractors
M/s. Knchan Associates
Consultants
M/s. Saolapurkar and Associates