Project Duration
Stipulated Date of Commencement
October 12 2018
Stipulated Date of Completion /
Likely Date of Completion September 02 2019
Likely Date of Completion September 02 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,127,060.00
Awarded for
₹ 1,823,808.00
Project highlights
SITC of 30KVA online UPS systems for ICU 123 and Modular OT 5 at Goa Medical College.
Contractors
M/s. Power Resources,
Consultants
In-house (GSIDC)
See Similar Projects
Interior works – Phase II.
View Project
Supply, Testing and Commissioning of Ventilators with Humidifiers
View Project
Minor maintenance and renovation works at Goa Dental College and Hospital, Bambollim,Goa.
View Project





