Project Duration
Stipulated Date of Commencement
February 14 2010
Stipulated Date of Completion /
Likely Date of Completion June 13 2010
Likely Date of Completion June 13 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,320,955.00
Awarded for
₹ 40,38,353.50
Contractors
M/s. Sunshine Electricals & Co. Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.