Project Duration
Stipulated Date of Commencement December 01 2018
Stipulated Date of Completion /
Likely Date of Completion
April 30 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,149,290.00
Awarded for ₹ 9,601,950.00

Project highlights

Construction of compound wall around the plot boundry

 
Gallery Image
Contractors
M/s. Race Constructions
Gallery Image
Consultants
M/s. Ulysis
 
Similar Projects

See Similar Projects

Similar Project

Repairs/Upgradation & Maintenance of Government High School & Primary School – Maina, Quepem, Goa.

View Project
Similar Project

Construction of Concrete Road for Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.

View Project
Similar Project

Repairs/Upgradation and Maintenance of Government Primary Schools in the State of Goa Sanguem Taluka – (GPS Periudak, GPS Devnamol, GPS Mugoli, GPS Taripanta, GPS Curpem)

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.