Project Duration
Stipulated Date of Commencement
December 01 2018
Stipulated Date of Completion /
Likely Date of Completion April 30 2019
Likely Date of Completion April 30 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,149,290.00
Awarded for
₹ 9,601,950.00
Project highlights
Construction of compound wall around the plot boundry
Contractors
M/s. Race Constructions
Consultants
M/s. Ulysis