Project Duration
Stipulated Date of Commencement December 01 2018
Stipulated Date of Completion /
Likely Date of Completion
April 30 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,149,290.00
Awarded for ₹ 9,601,950.00

Project highlights

Construction of compound wall around the plot boundry

 
Gallery Image
Contractors
M/s. Race Constructions
Gallery Image
Consultants
M/s. Ulysis
 
Similar Projects

See Similar Projects

Similar Project

Repairs/Upgradation and maintenance of Government schools in the state of Goa – Package B (GPS Hivre Budruk, GPS Pal, GPS Kudshe, GMS Kudshe)

View Project
Similar Project

Repairs/Upgradation & Maintenance of Govt. Schools in the State of Goa – (Ponda Taluka) – (GPS Opawada, Gauthan,Murdi & Zamole Khandepar)

View Project
Similar Project

Repairs/Upgradation & Maintenance of Govt. Schools in the State of Goa- (Ponda Taluka) – (GPS Konse, GPS Makadsai, GPS Gothawada,GPS Kodar,GPS Bonbag & GPS Shignewhal )

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.