Project Duration
Stipulated Date of Commencement
February 28 2015
Stipulated Date of Completion /
Likely Date of Completion August 27 2015
Likely Date of Completion August 27 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 40,000,000.00
Awarded for
₹ 40,000,000.00
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. Duracore Constructions
Consultants
M/s. Nitin Arolkar