Project Duration
Stipulated Date of Commencement
March 04 2014
Stipulated Date of Completion /
Likely Date of Completion April 03 2014
Likely Date of Completion April 03 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ -
Awarded for
₹ -
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. Duracore Constructions
Consultants
M/s. Nitin Arolkar