Project Duration
Stipulated Date of Commencement
November 13 2017
Stipulated Date of Completion /
Likely Date of Completion November 12 2018
Likely Date of Completion November 12 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 127,693,445.00
Awarded for
₹ 133,860,915.16
Project highlights
Olympic size Swimming Pool of size 50x25x2m.
Diving Pool of size 18x18x4.5m with RCC diving platforms for heights 1m. 3m. 5m & 7.5m.
Kids Pool of 150M2, Filtration Plant -200 m2.
Contractors
M/s. S.N. Construction
Consultants
M/s TPF Engineering Pvt. Ltd.
(Goa Regional Office)
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Sattari Taluka: Package-G (GHS Surla, GPS Surla, GPS Gholwada, GHS Keri)
View Project
Repairs/Upgradation and Maintenance of Government High school Shigao in Dharbandora taluka -Civil, plumbing, and electrical works
View Project
Repairs/ Upgradation & Maintaince of Government schools in the State of Goa – Civil, Plumbing & Electrical Woks – Canacona Package-II (GPS Baddem, GPS Avali, GPS Dabel, GHS Shristhal in Canacona Taluka)
View Project