Project Duration
Stipulated Date of Commencement
July 12 2018
Stipulated Date of Completion /
Likely Date of Completion May 21 2019
Likely Date of Completion May 21 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,393,091.00
Awarded for
₹ 9,980,231.26
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s.Anish Associates
Consultants
M/s.Nitin Arolkar