Project Duration
Stipulated Date of Commencement
June 22 2015
Stipulated Date of Completion /
Likely Date of Completion October 21 2015
Likely Date of Completion October 21 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,988,924.00
Awarded for
₹ 4,988,924.00
Project highlights
Repair/Upgrdation works of schools which includes roofing , tiling,dadoes,painting etc.
Contractors
M/s.Duracore Constructions
Consultants
M/s.Nitin Arolkar
See Similar Projects
Repairs/Upgratation & Maintenance of Govt Schools in the state of Goa – Package A (Sattari Taluka) – (GPS Gundelwada Velus, GPS Bhuipal, GPS Kopardem, GPS Dhamshe)
View Project
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil,Plumbing & Electrical works-Package J – Sattari Taluka – GPS Kumbharkand, GPS Tamitgi, GPS Kesarkarwada, GPS Bagwada
View Project
Construction of Compound Wall for Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.
View Project