Project Duration
Stipulated Date of Commencement
July 26 2019
Stipulated Date of Completion /
Likely Date of Completion August 04 2020
Likely Date of Completion August 04 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,666,709.00
Awarded for
₹ 14,181,390.28
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s. UVR Developers
Consultants
M/s. Nitin Arolkar
See Similar Projects
Repair,Upgradation & Maintenance of Government Schools in the State of Goa – Civil, Plumbing & Electrical Works – Bardez Taluka: GPS Munag, GPS Bamanwada, GPS Chivarband, GPS Chopdem & GPS Rai Siolim.
View Project
Repairs/Upgradation and maintenance of Government Schools in the state of Goa- Civil Plumbing and Electrical works:-Bicholim Taluka – Package K ( G.P.S Vathadev – Sarvan , G.P.S. Paltadwada, G.P.S. Naigini – Kudchire and G.P.S Kholpewadi – Sal )
View Project
Repairs & Upgradation and maintenance of Govt. Schools in the State of Goa. Package IB (Bardez Taluka)
View Project