Project Duration
Stipulated Date of Commencement
December 21 2018
Stipulated Date of Completion /
Likely Date of Completion May 20 2019
Likely Date of Completion May 20 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,062,232.00
Awarded for
₹ 9,584,411.00
Project highlights
Construction of internal concrete road joining school building and hostels and laying of pavers for footpath.
Contractors
M/s. Impact Infraheights Pvt. Ltd.,
Consultants
M/s. Ulysis