Project Duration
Stipulated Date of Commencement
July 27 2013
Stipulated Date of Completion /
Likely Date of Completion July 26 2014
Likely Date of Completion July 26 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,000,000.00
Awarded for
₹ 20,000,000.00
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s.M B Kinlekar
Consultants
M/s.Bhaskar Wagle & Associates
See Similar Projects
Repairs/Upgradation & Maintenance of Government High School at New Vaddem, Mormugao, Goa.
View Project
Upgradation/Renovation of Government College at Quepem, Goa – Interior Furniture works
View Project
Reconstruction of Government Primary School at Arla Querim – Civil, Plumbing and Electrical Works
View Project





