Project Duration
Stipulated Date of Commencement
March 07 2019
Stipulated Date of Completion /
Likely Date of Completion November 20 2019
Likely Date of Completion November 20 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,795,370.00
Awarded for
₹ 13,724,359.85
Project highlights
Repairs/Upgradation of School
Contractors
M/s. K. G. Thomas
Consultants
M/s. Creative Abode.
See Similar Projects
Repairs/Upgradation and Maintenance of Government Primary Schools in the State of Goa Sanguem Taluka – (GPS Periudak, GPS Devnamol, GPS Mugoli, GPS Taripanta, GPS Curpem)
View Project
Repairs/Upgradation and Maintenance of Govt. Schools in the state of Goa – Civil, Plumbing and Electrical works -Bicholim Taluka- Package B-(G.P.S. Amona, G.P.S. Digne Surla, G.P.S. Kharwada Amona, G.P.S. Maini Navelim, G.P.S. Nawarwada Pale, G.P.S. Rumad Surla, G.P.S.Khodgini Surla, G.P.S. Khajan Surla )
View Project
Extension / upgradation of Government college of Arts, Science & Commerce at Khandola, Marcel, Goa -HVAC work
View Project