Project Duration
Stipulated Date of Commencement
August 19 2019
Stipulated Date of Completion /
Likely Date of Completion December 31 2022
Likely Date of Completion December 31 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,016,611.35
Awarded for
₹ 18,098,805.51
Project highlights
Repair and Upgradation Work
Contractors
M/s. Shrusti Construction
Consultants
Creative Abode