Project Duration
Stipulated Date of Commencement February 22 2014
Stipulated Date of Completion /
Likely Date of Completion
April 21 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 24,959,508.00
Awarded for ₹ 30,014,958.00

Project highlights

Construction of GHS builing block with compound wall and external area development

 
Gallery Image
Contractors
M/s. Priority Construction
Gallery Image
Consultants
M/s. Prakash Lawande Associate
 
Similar Projects

See Similar Projects

Similar Project

Repairs /Upgradation & Maintenance of Government schools in the state of Goa -Civil,Plumbing & Electrical works – Package IV-B

View Project
Similar Project

Look and Image Operations for the Lusofonia Games, Goa – 2014.

View Project
Similar Project

Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Pernem Taluka: Package-IV (GPS Naikwada Palye, GPS Bhandarwada Palye, GPS Deulwada Mandre, GPS Naikwada Mandre, GPS Deulwada Morjim)

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.