Project Duration
Stipulated Date of Commencement November 30 2014
Actual Date of Completion August 30 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 12,385,911.40
Awarded for ₹ 16,443,238.00
 
Contractors
M/s. H. Candolcar & Sons
Consultants
M/s. Bhasker Wagle & Associates
 