Project Duration
Stipulated Date of Commencement
February 11 2014
Stipulated Date of Completion /
Likely Date of Completion February 25 2014
Likely Date of Completion February 25 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 860,362.00
Awarded for
₹ 885,228.00
Project highlights
The scope of work invloves installation of decorative street light poles along with the cabling work and providing foundations for street lights.