Project Duration
Stipulated Date of Commencement
January 19 2014
Actual Date of Completion
January 25 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 334,479,486.00
Awarded for
₹ 277,200,000.00
Final Cost of Project
₹ 278,941,656.00
Project highlights
The project consists of two lane composite steel girder bridge of 220 m length along with approaches of 1600 m on Amona side and 500 m on Virdi side. The bridge lighting is of signature high quality LED fittings.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Design and construction of Bridge across River Zuari between Amona and Virdi. SH: Supply of LED Fittings, Poles and Brackets
100% completed
Project Duration
Stipulated Date of Commencement
February 26 2018
Stipulated Date of Completion /
Likely Date of Completion July 05 2018
Likely Date of Completion July 05 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,399,120.00
Awarded for
₹ 2,820,440.00
Final Cost of Project
₹ 2,687,080.00
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates
See Similar Projects
Construction of bridge across river between Aldona and Calvim.
View ProjectHotmiixing of road in Fatorda for Lusofonia Games
View ProjectDesign & Construction of Bridge across river Zuari between Amona and Virdi.
View Project