Project Duration
Stipulated Date of Commencement
March 30 2007
Stipulated Date of Completion /
Likely Date of Completion June 29 2007
Likely Date of Completion June 29 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 23,855,472.00
Awarded for
₹ 22,488,455.00
Project highlights
The work comprises of providing and laying asphaltic concrete and bituminous macadam to the entire bus stand, depot and adjoining road.
Contractors
M/s. Madanant Constructions (Goa) Pvt. Ltd
Consultants
M/s. Vijaykumar Sawant Associates