Project Duration
Stipulated Date of Commencement
November 21 2013
Stipulated Date of Completion /
Likely Date of Completion January 19 2014
Likely Date of Completion January 19 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,455,439.00
Awarded for
₹ 17,090,650.00
Project highlights
Widening & hotmixing of roads
Contractors
M/s.Assmas Constructions Pvt. LTd
Consultants
M/s.Madhav Kamat & Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Widening of road in Calangute – Baga – Electrical works..
100% completed
Project Duration
Stipulated Date of Commencement
February 11 2014
Stipulated Date of Completion /
Likely Date of Completion February 25 2014
Likely Date of Completion February 25 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 860,362.00
Awarded for
₹ 885,228.00
Project highlights
The scope of work invloves installation of decorative street light poles along with the cabling work and providing foundations for street lights.
Contractors
M/s. Aditya Electromech Services
Consultants
In-house
(GSIDC)
See Similar Projects
Development works at Old Goa (Road connecting NH-4A to Miraculous Cross Church).
View Project
Design and Construction of bridge over river Kushawati at Adem, Sanguem Taluka.
View Project
Strengthening and Hot Mixing of road from Sanquelim to Karnataka State Border via Keri (Sattari Taluka) from Ch 0.00 to Ch. 26.50 Kms.
View Project