Project Duration
Stipulated Date of Commencement February 22 2014
Stipulated Date of Completion /
Likely Date of Completion
April 21 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 41,744,302.00
Awarded for ₹ 42,575,717.00

Project highlights

Internal Roads of total approximate length of 3.4 km hotmixed and widened at certain locations.

 
Gallery Image
Contractors
M/s. Shaurya Construction Pvt. Ltd.
Gallery Image
Consultants
M/s. Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Hot mixing & Improvement of Internal Roads in V. P. Navelim in Navelim Constituency.

View Project
Similar Project

Dismantling of HT overhead lines, supplying & laying of HT underground cables at Panaji – Cable work from EDC substation to Chimbel junction.

View Project
Similar Project

Construction of bridge across river between Aldona and Calvim.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.