Project Duration
Stipulated Date of Commencement February 22 2014
Stipulated Date of Completion /
Likely Date of Completion
April 21 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 41,744,302.00
Awarded for ₹ 42,575,717.00

Project highlights

Internal Roads of total approximate length of 3.4 km hotmixed and widened at certain locations.

 
Gallery Image
Contractors
M/s. Shaurya Construction Pvt. Ltd.
Gallery Image
Consultants
M/s. Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Upgradation & beautification of road network from Seraulim to Colva beach – Phase I.

View Project
Similar Project

Construction and upgradation of fishing jetty at Malim (North Goa) and Cortalim (South Goa).

View Project
Similar Project

Upgradation of road from Vodli to Kalay in Sanguem Taluka.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.