Project Duration
Stipulated Date of Commencement
June 01 2015
Stipulated Date of Completion /
Likely Date of Completion June 30 2015
Likely Date of Completion June 30 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 23,102,432.00
Awarded for
₹ 23,756,000.00
Project highlights
The scope of work involves Hotmixing of Road from Sai Service Junction to Training College Junction
Contractors
M/s. Ritesh Developers Pvt. Ltd.
Consultants
M/s. Nitin Arolkar