Project Duration
Stipulated Date of Commencement May 26 2006
Stipulated Date of Completion /
Likely Date of Completion
July 25 2006
Status
100%
Completed
Cost (₹)
Estimated at ₹ 26,014,669.00
Awarded for ₹ 32,205,615.00

Project highlights

Main work involved widening of existing road including hot mixing, improvement of existing drainage system, signages, etc. The approximate length of the road is around 8.2 kms

 
Gallery Image
Contractors
M/s. E. O. Thomas & Co.
Gallery Image
Consultants
M/s. Madhav Kamat & Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of Bridge across Rua de Ourem Creek, Panaji – Shifting of 11 KV Cable

View Project
Similar Project

Improvement and Upgradation of the road from Borim Bridge Junction to Kamaxi Temple and Shivnath Temple in Shiroda Constituency.

View Project
Similar Project

Construction of bridge at Guleli – Padeli in Sattari Taluka, Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.