Project Duration
Stipulated Date of Commencement
November 01 2005
Stipulated Date of Completion /
Likely Date of Completion December 30 2005
Likely Date of Completion December 30 2005
Status
100%
Completed
Cost (₹)
Estimated at
₹ 46,914,515.00
Awarded for
₹ 41,537,875.00
Project highlights
The work involved laying of DBM and AC carpet for road of approximately 14.2 km. from O’ Coqueiro to Calangute beach via St Anthony Chapel and from St. Anthony Chapel to Fort Aguada
Contractors
M/s. Sudin N. Verenker
Consultants
M/s. RITES Ltd.