Project Duration
Stipulated Date of Commencement
March 05 2014
Stipulated Date of Completion /
Likely Date of Completion August 04 2014
Likely Date of Completion August 04 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 21,102,630.00
Awarded for
₹ 22,784,504.40
Project highlights
Maintenance of bridges (South Goa)

Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.,

Consultants
Pre tender –
M/s. Kashec Engineers Pvt. Ltd.,
Post tender
In-house (GSIDC)