Project Duration
Stipulated Date of Commencement January 05 2004
Stipulated Date of Completion /
Likely Date of Completion
July 04 2004
Status
100%
Completed
Cost (₹)
Estimated at ₹ 11,750,000.00
Awarded for ₹ 12,880,000.00

Project highlights

• Length : 90 m.
• Carriage way 4.5 m wide with kerbs and railings on both the sides.
• Five spanned with two abutments and four piers all of which are resting on open foundation.

 
Gallery Image
Contractors
M/s. Descon
Gallery Image
Consultants
M/s. Kuvelkar Salkar Associates
 
Similar Projects

See Similar Projects

Similar Project

Providing and applying high build, crack building, electromeric, protective and waterproof coating to the Grade separator (2 flyovers) at Dabolim airport.

View Project
Similar Project

Construction of bridge at Guleli – Padeli in Sattari Taluka, Goa.

View Project
Similar Project

Refurbishment of Pedestrian Bridge linking Central Library and creek.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.