Project Duration
Stipulated Date of Commencement
January 08 2018
Stipulated Date of Completion /
Likely Date of Completion January 22 2018
Likely Date of Completion January 22 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,181,939.00
Awarded for
₹ 3,492,794.00
Project highlights
Providing Streetlight Poles from Colva circle to Ravindra bhavan Circle.
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
M/s. Ankit Prabhudessai
See Similar Projects
Supply, Installation, Testing and Commissioning of flag mast system at the new bridge across river Mandovi at Panaji, Goa. SH: Supply of 20ftX30 ft National Flag
View Project
Khareband Bridge.
View Project
Phase II