Project Duration
Stipulated Date of Commencement
October 08 2016
Stipulated Date of Completion /
Likely Date of Completion April 07 2017
Likely Date of Completion April 07 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,388,910.00
Awarded for
₹ 8,326,480.10
Project highlights
The scope of work includes Renovation of the existing police outpost.
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Nitin Arolkar