Project Duration
Stipulated Date of Commencement
February 22 2019
Stipulated Date of Completion /
Likely Date of Completion July 22 2019
Likely Date of Completion July 22 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ Rate contract of Rs.50,00,000.00
Project highlights
Repairs/Upgradation and maintenance of Government schools in the state of Goa – Sattari Taluka and Pernem Taluka
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Manoj M. Amshekar