Project Duration
Stipulated Date of Commencement
September 13 2018
Stipulated Date of Completion /
Likely Date of Completion January 12 2019
Likely Date of Completion January 12 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,268,481.00
Awarded for
₹ 3,842,318.00
Project highlights
Upgradation work including tiling, roofing, painting etc for observatory
Contractors
M/s.Atharva Infra Solutions
Consultants
M/s.Datta Kare Associates