Project Duration
Stipulated Date of Commencement September 13 2018
Stipulated Date of Completion /
Likely Date of Completion
January 12 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,268,481.00
Awarded for ₹ 3,842,318.00

Project highlights

Upgradation work including tiling, roofing, painting etc for observatory

 
Gallery Image
Contractors
M/s.Atharva Infra Solutions
Gallery Image
Consultants
M/s.Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of Sewage Treatment Plant at Sanquelim, Goa – Connection of houses to sewer lines.

View Project
Similar Project

Fire Fighting Works

View Project
Similar Project

Supply, installation, testing & commissioning of Interactive LED Panels and Video Conferencing system at newly constructed Office Building for Department of Forest at Altinho Old IPHB Complex

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.