Project Duration
Stipulated Date of Commencement
June 23 2015
Actual Date of Completion
September 22 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,066,421.00
Awarded for
₹ 4,545,045.00
Final Cost of Project
₹ 3,550,550.72
Contractors
M/s. Speedfrost Services Pvt. Ltd.
Consultants
M/s. Datta Kare Associates