Project Duration
Stipulated Date of Commencement
February 16 2010
Stipulated Date of Completion /
Likely Date of Completion August 15 2010
Likely Date of Completion August 15 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,33,96,780.00
Awarded for
₹ 21,149,474.00
Contractors
M/s. Imperial Engineering Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.
See Similar Projects
Carpentry and interior work.
View Project
Supply, installation, testing and commissioning of Precision AC, UPS, D. G. Set, Transformer, and related electrical works
View Project
External Electrical works.
View Project