Project Duration
Stipulated Date of Commencement
December 01 2011
Stipulated Date of Completion /
Likely Date of Completion March 31 2012
Likely Date of Completion March 31 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,058,320.00
Awarded for
₹ 2,406,250.00
Contractors
M/s. Megastar Engineering
Consultants
M/s. Datta Kare Associates